All Stops Accessible Program St. Charles Streetcar Project
Project Overview
In an effort to increase service reliability, rider safety, and accessibility along the St. Charles streetcar line, the RTA will be ensuring that all stops along the route are fully ADA-compliant by August 31, 2028. The project requires some stop consolidation and rebalancing, in line with RTA fixed-route service standards. Remaining stops will be brought into ADA and PROWAG compliance so that riders of all abilities may utilize the St. Charles streetcar service safely and comfortably.
Goals
- Full ADA-compliance by August 31, 2028
- Faster and more reliable streetcar service
- Increased safety for riders along the route
Timeline
| Fall 2026 | Design and Stop Consolidation Efforts Begin |
| Winter 2026-27 | Final Design Completed |
| Spring / Summer 2027 | Construction Bids Received and Contractor Selected |
| Summer 2027 – Summer 2028 | Construction |
| August 2028 | Project completion |